Sewer Project 2022

9/29/2022 & 10/03/2022

#FFFFFF

ATTENTION

Sewer Project Updates:

Tomorrow 9-29-2022:

Crossing State road Highway 149 at 10 1/2 street will be a one lane during the day. Both lanes will be open again by end of day Thursday.

Monday 10-03-2022:

Crossing State road Highway 149 at Loma one lane only during the day. Both lanes will be open at end of day.

9/26/22 - 9/30/22

#FFFFFF

Beginning Monday 9/26, RMS Utilities is scheduled to perform work on the Phase 2 sewer upgrade project by continuing to replace the sewer pipe on the west end of 10 1/2 Street.  They will be finishing up the last 2 lateral connections and ending the main sewer replacement near the CDOT  HWY 149 right of way.

RMS will then relocate and start the pipe replacement located in the outfield of the baseball field at Hargrave's Park.  (see map).  They will be concentrating on the area  just south of HWY 149 (near the end of the parking lot and the OHV/ATV trail) during this time frame.

The pipe replacement work crossing HWY 149 near this location and at 10 1/2 Street is tentatively scheduled for the week of 10/3 -10/7.

 

The RMS Utilities asphalt crew is scheduled to perform asphalt replacement work on Monday 9/26 at La Garita, and on Bee McClure near Rue La Fong.  (See maps).  Temporary delays and road closures can be expected during the asphalt installation process, so please plan ahead and/or reroute accordingly.  (OHV's and 4 wheelers will have continued access on La Garita). Your patience with the crew during this time is appreciated.

 

****This schedule is subject to change due to inclement weather, asphalt plant availability, and/or any underground construction issues that may be found.****